As part of the Council's 4 year investment programme to 'Protect, Care and Invest to create a better borough'. Between 2020 and 2024 over £50m is being invested to keep neighbourhoods safe, clean and well connected. The 'Pride in our Community' Highways Capital Programme will deliver improvements to infrastructure including roads, footpaths, parking, sustainable transport, street furniture, drains and structures.
Our highways vision is to 'Keep Telford Moving' and in 2021/2022 we will invest £21.6m to deliver over 160 improvement schemes across the borough.
Road Maintenance: Surface Treatment Schemes
A programme of Surface Treatment is due to commence on various sites (see Resident Letter for a list of sites with forecasted dates) on 10 May 2021 between the hours of 7.30am and 6pm. The works are a two stage process requiring two applications. This means that Contractors and Traffic Management will visit each site twice, please refer to the Resident Letter for programme dates. The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council's highway capital programme as part of its 'Pride in Our Community' programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Surface Dressing (RMS) and lining (WJ UK).
Detailed Works Programme
- The works will be managed under Stop and Go / Convoy working. This means that access through sites will be mostly maintained, apart from short periods where the material must harden.
- Residents and businesses directly affected will receive an information leaflet and resident letter 24/48 hours prior to contractors arriving on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Surface Treatment Scheme
We are planning to carry out Surface Treatments to improve the condition of the highway.
Provisional start and end dates
- Start date 2 June 2021.
- End date: 18 June 2021.
Proposed Traffic Management Arrangements
Traffic will be managed by using Stop and Go/Convoy working.
Proposed Working Hours
Road Maintenance: A5 Telford Way (Hollinswood Roundabout to Priorslee Roundabout) Resurfacing Scheme
A programme of resurfacing is due to commence on A5 Telford Way (Hollinswood Roundabout to Priorslee Roundabout) on 4 May 2021 and be completed by 12 May (Weekdays only 8am - 6pm). The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council's highway capital programme as part of its 'Pride in Our Community' programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum), Loop Installation (Dynniq) and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below.
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
A5 Telford Way (Hollinswood Roundabout to Priorslee Roundabout) Resurfacing Scheme
We are planning to carry out resurfacing A5 Telford Way (Hollinswood Roundabout to Priorslee Roundabout) to improve the condition of the highway.
Provisional dates
- Start date 4 May 2021.
- End date: 12 May 2021.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works
Proposed Working Hours
Road Maintenance: A442 Trench Lock Interchange to Wombridge Interchange Southbound Resurfacing Scheme
A programme of resurfacing is due to commence on A442 Trench Lock Interchange to Wombridge Interchange Southbound on 26 April 2021 and be completed by 5 May 2021 (Weekdays only 8am - 6pm and excluding the Bank Holiday). The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council's highway capital programme as part of its 'Pride in Our Community' programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below.
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
A442 Trench Lock Interchange to Wombridge Interchange Southbound Resurfacing Scheme
We are planning to carry out Resurfacing Scheme on A442 Trench Lock Interchange to Wombridge Interchange Southbound to improve the condition of the highway.
Provisional Dates
- Start date: 26 April 2021.
- End date: 5 May 2021.
Traffic Management will be removed over the weekend and Bank Holiday.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works
Proposed Working Hours
- 8am - 6pm.
- Download the Resident / Business Letter for more information on A442 Trench Lock Interchange to Wombridge resurfacing scheme.
- Download the Diversion map plan to see alternative routes to use during A442 Trench Lock Interchange to Wombridge resurfacing scheme.
- Download scheme construction drawing number one to see plans for A442 Trench lock Interchange to Womberidge resurfacing scheme.
- Download scheme construction drawing number two to see plans for A442 Trench lock Interchange to Womberidge resurfacing scheme.
- Download scheme construction drawing number three to see plans for A442 Trench lock Interchange to Womberidge resurfacing scheme.
Road Maintenance: Wrockwardine Wood Way Resurfacing Scheme
A programme of resurfacing is due to commence on Wrockwardine Wood Way on 9 August 2021 and be completed by 16 August 2021. The works will be carried out under a 24 hour Road Closure, which will be in place on weekdays only. The work is, however, weather dependant and the programme dates shown may be subject to change.
The funding for the work has come from the Council's highway capital programme as part of its 'Pride in Our Community' programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Wrockwardine Wood Way Resurfacing Scheme
We are planning to carry out resurfacing of Wrockwardine Wood Way to improve the condition of the highway.
Provisional Dates
- Start date: 9 August 2021.
- End date: 16 August 2021.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works.
Proposed Working Hours
- 7am - 5pm
- Download the Resident / Business Letter for more information on Wrockwardine Wood Way resurfacing scheme.
- Download the Diversion map plan to see alternative routes to use during the Wrockwardine Wood Way resurfacing scheme.
- Download scheme Construction' Drawing one to see plans for the Wrockwardine Wood Way resurfacing scheme.
Road Maintenance: Dale End to Jiggers Bank (Darby Road Junction) Scheme
A programme of Patching is due to commence on Dale End to Jiggers Bank (Darby Road Junction) on 2 August 2021 for 2 weeks. The works will be carried out under a Dynamic Road Closure, which will be in place between 8am - 5pm, on weekdays only. The hard road closure point will be moved up the road, when sections of the works have been completed. The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council's highway capital programme as part of its 'Pride in Our Community' programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Premier), Ironwork (Premier), Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Access will be maintained to residents and coordinated by onsite Traffic Operatives.
- Access will be maintained to Ironbridge Medical Practice throughout the works and managed by on site Traffic Operatives.
- Customers of Dale End Café and Brooke Evans Ironbridge hairdressers are advised to use Dale End Car Park for parking, footpaths will be open throughout to maintain pedestrian access.
- It is advised for residents to get access to Paradise via the Wharfage End, if this is not possible, access will be managed by on site Traffic Operatives.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Dale End to Jiggers Bank (Darby Road Junction) Scheme
We are planning to carry out Patching on Dale End to Jiggers Bank (Darby Road Junction) Scheme to improve the condition of the highway.
Provisional Dates
- Start date: 2 August 2021.
- End date: 13 August 2021.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter/diversion plan attached), which will be clearly signed throughout the works.
Proposed Working Hours
- 8am - 5pm
- Download the Resident/Business Letter for more information on Dale End to Jiggers Bank resurfacing scheme.
- Download the Diversion map plan to see alternative routes to use during the Dale End to Jiggers Bank resurfacing scheme.
- Download the scheme Construction Drawing one to see plans for the Dale End to Jiggers Bank resurfacing scheme.
- Download the scheme Construction Drawing two to see plans for the Dale End to Jiggers Bank resurfacing scheme.
Road Maintenance: Hurleybrook Way Resurfacing Scheme
A programme of resurfacing is due to commence on Hurleybrook Way on 9 August 2021- 3 September 2021 (Civils work - With Minor Traffic Management) and 6 September 2021 - 17 September 2021 (Resurfacing and lining work - Under phased closures). The works will be carried out under Give and Take traffic management for the civils works then daily Road Closures for the surfacing works, which will be in place on weekdays only. We will be working between 7.30am - 5pm on weekdays. The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council's highway capital programme as part of its 'Pride in Our Community' programme to make the borough a better place to live, work and visit.
Closer to the time of the resurfacing works, we will update residents with a programme of the phased road closures, so that times of reduced access can be better communicated.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme
- For the resurfacing works road closures will be used at the site with access to frontages, however there may be periods with no access.
- Site specific designs and diversion routes can be found below.
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
We are planning to carry out resurfacing of Hurleybrook Way to improve the condition of the highway.
Provisional Dates
- Start date: 9 August 2021.
- End date: 17 September 2021.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure with access to frontages maintained (for further details please see resident letter and Traffic Management Drawing attached), which will be clearly signed throughout the works.
Proposed Working Hours
- 7am - 5pm
- Download the Resident/Business Letter for more information on the Hurleybrook Way resurfacing scheme.
- Download the Traffic Management Drawing to see alternative routes to use during the Hurleybrook Way resurfacing scheme.
- Download the scheme Construction Drawing to see plans for the Hurleybrook Way resurfacing scheme.
Road Maintenance: Charlton Street and Vicar Street Resurfacing Scheme
A programme of resurfacing is due to commence on Charlton Street and Vicar Street on 9 August 2021 and 27 August 2021. The phasing for the works will be as follows:
- 9 August 2021 - 13 August 2021 Civils Works (Minor traffic management)
- 16 August 2021 - 18 August 2021 Planning Out and Binder Surfacing (Phased road closures)
- 18 August 2021 - 25 August 2021 Civils Works (Phased road closures)
- 25 August 2021 - 27 August 2021 Surfacing Works (Phased road closures).
We will be working between 7.30am - 5pm on weekdays. The work is, however, weather dependant and the programme dates shown may be subject to change.
The funding for the work has come from the Council's highway capital programme as part of its 'Pride in Our Community' programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Charlton Street and Vicar Street Resurfacing Scheme
We are planning to carry out resurfacing of Charlton Street and Vicar Street to improve the condition of the highway.
Provisional Dates
- Start date: 9 August 2021.
- End date: 27 August 2021.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works.
Proposed Working Hours
- 7.30am - 5pm
- Download the Resident/Business Letter for more information on the Charlton Street and Vicar Street resurfacing scheme.
- Download the Diversion map plan to see alternative routes to use during the Charlton Street resurfacing scheme Phase 1.
- Download the Diversion map plan to see alternative routes to use during the Charlton Street resurfacing scheme Phase 2.
- Download the Diversion map plan to see alternative routes to use during the Vicar Street resurfacing scheme.
- Download the Scheme Construction Drawing to see plans for the Charlton Street and Vicar Street resurfacing scheme.
Road Maintenance: Hadley Park Roundabout Remedial Works
A programme of resurfacing is due to commence on Hadley Park Roundabout on Friday 13 August 2021 (7pm - 2am). The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council's highway capital programme as part of its 'Pride in Our Community' programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac) and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific diversion routes can be found below.
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Hadley Park Roundabout Remedial Works
We are planning to carry out remedial works on Hadley Park Roundabout to improve the condition of the highway.
Provisional Dates
- Start date: 13 August 2021.
- End date: Morning of 14 August 2021.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works
Proposed Working Hours
- 7pm - 2am.
- Download the Resident/Business Letter for more information on the Hadley Park Roundabout Remedial Works.
- Download the Diversion map plan 1 for alternative routes and traffic management for the Hadley Park Roundabout Remedial Works.
- Download the Diversion map plan 2 for alternative routes and traffic management for the Hadley Park Roundabout Remedial Works.
Road Maintenance: The Wharfage Resurfacing and Drainage Repair Scheme
A programme of resurfacing is due to commence on The Wharfage from 6 September 2021 and be completed by 15 October 2021 (including weekends). The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork & Drainage Works (G & N Groundworks), (Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
The Wharfage Resurfacing Scheme
We are planning to carry out resurfacing and drainage works on The Wharfage to improve the condition of the highway.
Provisional Dates
- Start Date: 6 September 2021
- End Date: 15 October 2021
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works
Proposed Working Hours
- 8am - 7pm (24 Hour Closure).
- Download the Resident/Business Letter for more information on The Wharfage Ironbridge Resurfacing and Drainage Repair Scheme.
- Download The Wharfage, Ironbridge Environment Agency advanced notice of essential road closure Resident Letter.
- Download the Diversion Map Plan for alternative routes during the closure for The Wharfage Resurfacing and Drainage Repair Scheme.
A programme of resurfacing is due to commence on The Lloyds/Coalport High Street Junction from 13 October 2021 and be completed by 15 October 2021. Please note Severn Trent Water will also be working collaboratively within the closure to install a new connection outside Number 35 Coalport High Street. The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork and Drainage Works (G & N Groundworks), (Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Provisional Dates
- Start Date 13 October 2021.
- End Date: 15 October 2021.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works
Proposed Working Hours
Road Maintenance: Admaston Road Resurfacing and Drainage Repair Scheme
A programme of resurfacing is due to commence on Admaston Road on 1 November 2021 and 20 November 2021. The works will be carried out under Phased Road Closures between the hours of 8am - 5pm. The work is, however, weather dependant and the programme dates shown may be subject to change. A summary of the Road Closure Phasing is shown below:
- Removal of Existing Speed Cushions and Drainage Investigations – 1 November 2021 - 3 November 2021 – Stop and Go Traffic Management
- Phase 1 – 4 November 2021 - 5 November 2021 Plane and Binder Course
- Phase 2 – 8 November 2021 - 9 November 2021 lane and Binder Course and Civils Works
- Phase 1 – 10 November 2021 - 13 November 2021 Civils Works
- Phase 1 – 15 November 2021 Surface Course
- Phase 2 – 16 November 2021 Surface Course
- Phase 1 and 2 (Alternated) – 17 November 2021 – 19 November 2021 Speed Cushion Installation
- Phase 1 and 2 (Alternated) – 20 November 2021 Road Markings.
Phase 1 is a closure from Wrockwardine Road to half way across the Elmpark Drive junction. Phase 2 is a closure from half way across Elmpark Drive junction to Donnerville Close.
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork and Drainage Work (G & N Groundworks), Traffic Management (Quantum), Speed Cushion removal and Installation (MSM Hire) and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
- Access will be maintained for residents of Admaston Road, Donnerville Gardens, Donnerville Close, Sweet Chariot Way, Elmpark Drive, Sycamore Close, Beech Close, Poplar Drive, Chestnut Drive and Paddock Close and facilitated by on site Traffic Management Operatives. There will however be short periods; when the road surface is planed out and the new surfacing material is hardening, where access will be temporarily restricted.
Provisional Dates
- Start Date 1 November 2021.
- End Date: 20 November 2021.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion, which will be clearly signed throughout the works. For further details please see resident letter/diversion plan.
Proposed Working Hours
- 8am - 5pm.
- Download the Resident/Business Letter for more information on Admaston Road Resurfacing and Drainage Repair Scheme.
- Download the scheme Construction Drawing for Admaston Road Resurfacing and Drainage Repair Scheme.
- Download the diversion plan for phase 1 Admaston Road Resurfacing and Drainage Repair Scheme.
- Download the diversion plan for phase 2 Admaston Road Resurfacing and Drainage Repair Scheme.