As part of the Council’s 4 year investment programme to Protect, Care and Invest to create a better borough, between 2020 and 2024 we are investing over £50m to keep neighbourhoods safe, clean and well connected. The ‘Pride in Our Community’ programme will deliver improvements to infrastructure including roads, footpaths, parking, sustainable transport, street furniture, drains and structures.
Our highways vision is to ‘Keep Telford Moving’ and in 2022/2023 we will invest £19.67m to deliver over 180 improvement schemes across the borough.
Prior to works commencing, detailed project information will be accessible below. Major schemes include:
Road Maintenance: Bennetts Bank, Highway Improvement Scheme
As part of the Council’s ongoing investment into its roads and footpaths, we will shortly be carrying out Various Works on Bennetts Bank, Wellington. Works include: Carriageway Resurfacing/Re-alignment, New Parking Bays, Footway Works, Drainage Works, New Bus Stop, and Road Markings, this programme of works is due to start on the 14 March 2022 and completed by 6 May 2022, between the hours of 8am and 5pm. The work is, however, weather dependant and the programme dates shown may be subject to change.
The funding for the work has come from the Council's highway capital programme as part of its 'Pride in Our Community' programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Civil Works (G&N), resurfacing works (Tarmac) and lining (WJ UK).
Detailed Works Programme
- The works will be managed under a Lane closure for Westbound traffic in the most part with evening full closures on the 2 May 2022 – 6 May 2022. Any traffic management used will be in place for the duration of the scheme dates to facilitate the works.
- Site specific designs, diversion routes and phasing plans can be found below.
- Residents and businesses directly affected will receive an information leaflet and resident letter 2 weeks prior to contractors arriving on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Provisional start and end dates
- Phase 1 - 14 March 2022 - 8 April 2022 – 24 hour Lane Closure - Westbound from Ketley Brook Roundabout to Cock Hotel Traffic Signals.
- Phase 2 – 11 April 2022 - 29 April 2022 – 24 hour Lane Closure - Westbound from Ketley Brook Roundabout to Cock Hotel Traffic Signals.
- Phase 3 – 2 May 2022 - 6 May 2022 – Road Closure (In place between 6.30pm - 6am).
Proposed Traffic Management Arrangements
The works will be managed under a Lane closure for Westbound traffic for the most part with evening full closures on the 2 May 2022 – 6 May 2022. Any traffic management used will be in place for the duration of the scheme dates to facilitate the works.
Proposed Working Hours
Road Maintenance: Surface Treatment Schemes (Surface Dressing)
A programme of Surface Dressing is due to commence on various sites (please see link to programme below, which will be updated throughout the scheme) on 26 April 2022 between the hours of 8am and 5pm. The works are a two-stage process requiring two applications. This means that Contractors and Traffic Management will visit each site twice, please refer to the Resident Letter for programme dates. Following this, reapplication of lining will commence shortly after. The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council's highway capital programme as part of its 'Pride in Our Community' programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Surface Dressing (RMS) and lining (WJ UK).
Detailed Works Programme
- The works will be managed under Stop and Go/Convoy working. This means that access through sites will be mostly maintained, apart from short periods where the material must harden.
- Residents and businesses directly affected will receive an information leaflet and resident letter 24/48 hours prior to contractors arriving on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Surface Treatment Scheme
We are planning to carry out Surface Treatments to improve the condition of the highway.
Provisional start and end dates
- Start date: 26 April 2022 (Surface Dressing).
- 9 May 2022 (Re-lining).
- End date: 11 May 2022 (Surface Dressing).
- 14 June 2022 (Re-lining).
Proposed Traffic Management Arrangements
Traffic will be managed by using Stop and Go/Convoy working.
Proposed Working Hours
A programme of resurfacing is due to commence on Redhouse Roundabout on 18 October 2022 to 24 October 2022 (Nights 7pm - 7am). The work is, however, weather dependant and the programme dates shown may be subject to change.
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Redhouse Roundabout Resurfacing
We are planning to carry out resurfacing on Redhouse Roundabout to improve the condition of the highway.
Provisional dates
- Start date: 18 October 2022.
- End date: 24 October 2022.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works
Proposed working hours
Road Maintenance: Cotwall Lane Resurfacing Scheme
A programme of resurfacing is due to commence on Cotwall Lane on 5 September 2022 and end 15 September 2022 (2 Way lights and then daytime closures) The work is, however, weather dependant and the programme dates shown may be subject to change.
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork, kerbing, drainage and signage (G & N Groundworks), Traffic Management (Quantum) and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Cotwall Lane Resurfacing Scheme
We are planning to carry out resurfacing on Cotwall Lane to improve the condition of the highway.
Provisional dates
- Start date: 5 September 2022
- End date: 15 September 2022
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works
Proposed Working Hours
Scheme information will be presented 2 weeks prior to scheme starting. If you require any further information prior, please contact highways@telford.gov.uk.
Road Maintenance: Dawley Bank Roundabout Resurfacing Scheme
A programme of resurfacing is due to commence on Dawley Bank Roundabout on 10 October 2022 to 17 October 2022 (7pm - 6am) The work is, however, weather dependant and the programme dates shown may be subject to change.
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum), and lining (WJ UK).
Detailed works programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below.
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
We are planning to carry out resurfacing on Dawley Bank Roundabout to improve the condition of the highway.
Provisional dates
- Start date 10 October 2022.
- End date: 17 October 2022.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works.
Proposed working hours
A programme of resurfacing is due to commence on Woodside Roundabout on 29 September 2022 to 17 October 2022 (7pm - 6am) The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Miles Macadam), Ironwork (Miles Macadam), Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
We are planning to carry out resurfacing on Woodside roundabout to improve the condition of the highway.
Provisional Dates
- Start date: 29 September 2022.
- End date: 17 October 2022.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works
Proposed working hours
Road Maintenance: Turreff Avenue Resurfacing Scheme.
A programme of resurfacing is due to commence on Turreff Avenue on 17/10/2022-26/10/2022 (07:30-17:30 and 1 day 19:00-06:00) The work is however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Miles Macadam), Ironwork (Miles Macadam), Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
We are planning to carry out resurfacing on Turreff Avenue to improve the condition of the highway.
Provisional Dates
- Start Date: 17 October 2022
- End Date: 26 October 2022
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan below), which will be clearly signed throughout the works.
Proposed Working Hours
Road Maintenance: Sinclair Garden Estate resurfacing scheme
A programme of resurfacing is due to commence on Sinclair Garden Estate on 31 August 2022 and be completed by 13 September 2022 (weekdays only), The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely, and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
We are planning to carry out patching on Sinclair Garden Estate to improve the condition of the highway.
Provisional dates
- Start date: 31 August 2022.
- End date: 13 September 2022.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan below), which will be clearly signed throughout the works.
Proposed working hours
Scheme information will be presented 2 weeks prior to scheme starting. If you require any further information prior, please contact highways@telford.gov.uk.
Scheme information will be presented 2 weeks prior to scheme starting. If you require any further information prior, please contact highways@telford.gov.uk.
Road Maintenance: Waterloo Road Resurfacing Scheme, Hadley
A programme of resurfacing is due to commence on Waterloo Road, Hadley on 24/10/22 – 31/10/22 from 7pm-7am. The work is however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum) and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Waterloo Road, Hadley Resurfacing Scheme
We are planning to carry out resurfacing on Waterloo Road, Hadley to improve the condition of the highway.
Provisional Dates
- Start Date 24 October 2022
- End Date: 31 October 2022
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan below), which will be clearly signed throughout the works.
Proposed Working Hours
- 7pm - 7am
- Download resident letter
- Download diversion plan for Waterloo Road, Hadley
- Download the full resurfacing plan
Road Maintenance: Brands Farm Way Resurfacing Scheme
A programme of resurfacing is due to commence on Brands Farm Way on 26 August 2022 and be completed by 10 September 2022 (weekdays only), The work is, however, weather dependant and the programme dates shown may be subject to change:
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum), and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely, and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Brands Farm Way Resurfacing Scheme
We are planning to carry out patching on Brands Farm Way to improve the condition of the highway.
Provisional Dates
- Start date: 30 August 2022.
- End date: 10 September 2022.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works.
Proposed Working Hours
A programme of resurfacing is due to commence on Pool Hill Road on 2 November 2022 - 4 November 2022 8am - 5.30pm The work is, however, weather dependant and the programme dates shown may be subject to change.
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (G & N Groundworks), Traffic Management (Quantum) and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below.
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
Pool Hill Road Resurfacing Scheme
We are planning to carry out resurfacing Pool Hill Road to improve the condition of the highway.
Provisional dates
- Start date 2 November 2022.
- End date: 4 November 2022.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works
Proposed Working Hours
Scheme information will be presented 2 weeks prior to scheme starting. If you require any further information prior, please contact highways@telford.gov.uk.
Scheme information will be presented 2 weeks prior to scheme starting. If you require any further information prior, please contact highways@telford.gov.uk.
Scheme information will be presented 2 weeks prior to scheme starting. If you require any further information prior, please contact highways@telford.gov.uk.
Road Maintenance: A442 Hollinswood to Brockton Resurfacing Scheme
A programme of resurfacing is due to commence on A442 Hollinswood to Brockton Resurfacing on 22 July 2022 to 3 September 2022 (nights and days). The work is, however, weather dependant and the programme dates shown may be subject to change.
The £1.5million funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
Following on from the extensive programme of works replacing the central reservation with hardstanding and vehicle restraint system replacements along the A442 between Hollinswood Interchange and A4169 Castlefields Roundabout, we are now scheduling a large-scale carriageway resurfacing scheme consisting of over 7,000 tons of carriageway surfacing, 13,000m of white lining and 1,200 road studs. The works have been carefully planned to be undertaken during the final stages of the ongoing works, and to coincide with the school summer holiday period to minimise overall disruption on the network, utilising 24 hour working to keep the programme as short as possible. The resurfacing will ensure that this section of carriageway is fully upgraded in order to reduce future maintenance needs and therefore reducing the need for further disruption on the network.
Works are planned for a 6 week period under 24 hour phased closures with diversion routes in place. The works will affect the North bound carriageway between Brockton Interchange and Hollinswood Interchange, and South bound between Stirchley Interchange and Brockton Interchange. Phased closures are as listed below:
- Randlay to Hollinswood Northbound - 22 July 2022 to 30 July 2022
- Stirchley to Randlay Northbound - 31 July 2022 to 7 August 2022
- Brockton Loops to Stirchley Northbound - 8 August 2022 to 13 August 2022
- Stirchley to Brockton Southbound – 14 August 2022 to 21 August 2022
- Hollinswood Interchange (Partial Resurfacing and Bridge Joints) – 17 August 2022 to 2 September 2022
- Randlay Interchange (Patching and Bridge Joints only) – 29 August 2022 to 3 September 2022.
Detailed Works Programme
- Phased closures will be utilised on site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
A442 Hollinswood to Brockton Resurfacing Scheme.
We are planning to carry out resurfacing on A442 Hollinswood to Brockton to improve the condition of the highway.
Provisional dates:
- Start date: 22 July 2022
- End date: 3 September 2022.
Proposed traffic management arrangements
Traffic will be managed by using a road closure and diversion (for further details please see diversion plans attached), which will be clearly signed throughout the works
Proposed Working Hours
- 24 hours.
- Download the diversion plan for the 22 July 2022 to 30 July 2022 for the A442 Northbound - Randlay Interchange to Hollinswood Interchange - Phase 1.
- Download the diversion plan for the 31 July 2022 to 7 August 2022 for the A442 Northbound - Stirchley to Randlay Interchange - Phase 2.
- Download the diversion plan for the 28 August 2022 to 13 August 2022 for the A442 Northbound - Brockton Roundabout to Stirchley - Phase 3.
- Download the diversion plan for the 14 August 2022 to 14 August 2022 for the A442 Southbound - Randlay to Brockton Interchange - Phase 4.
- Download the diversion plan for the 15 August 2022 to 21 August 2022 for the A442 Southbound - Randlay to Brockton Interchange - Phase 4A.
- Download the diversion plan for the 17 August to 19 August 2022 Day time - Hollinswood Interchange - Phase 5
- Download the diversion plan for the 22 August to 22 August 2022 Night time - Hollinswood Interchange - Phase 5
- Download the diversion plan for the 23 August to 23 August 2022 Night time - Hollinswood Interchange - Phase 5
- Download the diversion plan for the 24 August to 25 August 2022 Night time - Hollinswood Interchange - Phase 5
- Download the diversion plan for the 26 August to 30 August 2022 Day time - Hollinswood Interchange - Phase 5
- Download the diversion plan for the 29 August to 3 September 24hr Closure – Randlay Interchange - Phase 6
- Download Construction Drawing 1 - A442 Resurfacing 1 of 5.
- Download Construction Drawing 2 - A442 Resurfacing 2 of 5.
- Download Construction Drawing 3 - A442 Resurfacing 3 of 5.
- Download Construction Drawing 4 - A442 Resurfacing 4 of 5.
- Download Construction Drawing 5 - A442 Resurfacing 5 of 5.
- Download Construction Drawing 6 – Hollinswood Interchange 1 of 2.
- Download Construction Drawing 7 – Hollinswood Interchange 2 of 2.
- Download Construction Drawing 8 – Randlay Interchange.
A programme of resurfacing is due to commence on A41 Forton on 4 October 2022 to 10 October 2022 (Nights 7pm - 6am) The work is, however, weather dependant and the programme dates shown may be subject to change.
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit.
The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Traffic Management (Quantum) and lining (WJ UK).
Detailed Works Programme
- Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
- Site specific designs and diversion routes can be found below
- Where closures are in force, a diversion will be signed on site.
- Advanced information signs will be placed on each site 2 weeks prior to works commencing.
We are planning to carry out resurfacing on A41 Forton to improve the condition of the highway.
Provisional dates
- Start date 4 October 2022.
- End date: 10 October 2022.
Proposed Traffic Management Arrangements
Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works.
Proposed working hours
Last updated: 17/08/2023 11:40