The full range of work includes:
- removal of existing kerb line
- laying of new kerb line
- removal of existing paving slabs
- replacing and resetting of ironwork
- installation of new gullies and connections
- resurfacing of footpaths
- paving of footpaths
- planing and resurface of carriageway
- installation of new signage and bollards
- road markings.
Phase 1 A – From the railway bridge north of Station Approach through to the narrow section entering Market Street.
Phase 1 B - From the narrow section when entering Market Street up to Wilkinsons Car Park.
Phase 1 A will start on the 6 September 2022 and will move onto Phase 1 B, both of these sections will be completed prior to December to reduce the impact on Christmas trading.
Phase 2 – From Wilkinsons Car Park through to Bridge Street / Grooms Alley junction.
Phase 2 – Will take place in January following Christmas Period. Detailed programme to follow.
Due to the whole street scene being improved, traffic management will need to be in place 24 hours a day (access through the one way street will be opened each night where possible), access will be maintained throughout for emergency vehicles and where safe, service vehicles, pedestrian access to businesses will be maintaned at all times. We will have dedicated traffic management officers on site for the duration of the scheme to help with this provision.
Last updated: 19/08/2022 09:32